Construction at the Dharnya is all but completed. The final pieces of work, being the connection paths and undercover walkways (Bunkhouse to New DC building, new building to original building) have now been completed.
Our Woka Walla team are well down the path with Stage 1 of the landscaping and its very impressive. We are very keen to see the finished product.
A big Thank You to Graham and the Woka Walla team.
We have started the testing of the new building, Audio, Visual, WiFi and the like, with the last full YYTOLMB meeting held at the new building, as part of our progression. It’s important that we can test our equipment, to ensure we have everything working properly as we get closer to the official opening.
Over the course of the next month, we will look to test all of the equipment across the new Dharnya site, including setting up the Bunkhouse, the bunk rooms, bathrooms and appropriate signage, across the site.
Much is now completed but we still have plenty ahead of us.